Authenticated is false

Sutton Street

office building

Sutton Street

6 Sutton Street, Kooyong, 3144

Anticipated Completion Mid 2026

Information

June 2025

Dear Sutton Street Community,

We’re pleased to provide the latest construction update for Sutton Street, where progress continues steadily across site.

Key milestones to date:
• Partial Ground Floor concrete slab successfully poured (as of site inspection on 5 June 2025)
• Remaining Ground Floor slab expected to have been completed since
• Basement walls fully constructed
• Installation of essential services underway

What’s next:
• First Floor slab scheduled to be poured in early July
• Vertical structure works for Level 1 to commence shortly after (subject to weather conditions)

Overall project status:
• Construction pace has returned to a steady and consistent rhythm
• Project remains on track for completion by end of June 2026

We look forward to keeping you informed as the build progresses.

Kind regards,
The Sutton Design Team

www.suttonstreet.com.au

person