May 2025
Dear Sutton Street Purchaser,
Thank you for your continued patience and support as we now provide an update on the progress of the Sutton Street project.
Unfortunately, unforeseen delays occurred at the end of 2024, and just as the basement construction was nearing completion. As a result, there were then on-site delays during January and February this year.
Pleasingly, these setbacks have been resolved, and construction activity then resumed in March, regained significant momentum. The basement structure is now complete, and work has progressed to the Ground Floor level, with the Ground Floor concrete slab scheduled to be poured mid-month.
The builder and design team are now making every endeavor to recover from these earlier delays; however, the estimated completion date has been revised to mid-2026.
Thank you once again for your ongoing support —we look forward to bringing this exciting project to life and sharing more updates with you as work progresses.
Kind regards,
The Sutton Design Team