June 2025
Dear Sutton Street Community,
We’re pleased to provide the latest construction update for Sutton Street, where progress continues steadily across site.
Key milestones to date:
• Partial Ground Floor concrete slab successfully poured (as of site inspection on 5 June 2025)
• Remaining Ground Floor slab expected to have been completed since
• Basement walls fully constructed
• Installation of essential services underway
What’s next:
• First Floor slab scheduled to be poured in early July
• Vertical structure works for Level 1 to commence shortly after (subject to weather conditions)
Overall project status:
• Construction pace has returned to a steady and consistent rhythm
• Project remains on track for completion by end of June 2026
We look forward to keeping you informed as the build progresses.
Kind regards,
The Sutton Design Team