Society Armadale

building

Society Armadale

79-83 Wattletree Road, Armadale, 3143

Anticipated Completion December 2025

Information

Project Progress

100%

Demolition

100%

Structure

90%

Basement

47%

Fitout

September 2025

Dear Society Purchaser,

We are delighted to bring you the construction update for the Society development, detailing the progress on-site.

As we move into the warmer months, on-site progress continues to build momentum across the project.

  • Window installation is now largely complete enabling steady progress on fit-out.
  • Internal services rough-in and wall framing are complete up to Level 3;
  • Ceiling framing is complete on Level 1 and underway on Level 2.
  • Plastering is well progressed on Level 1 and has commenced on Level 2;
  • Tiling is complete on the Ground Floor and underway on Level 1; and
  • Internal painting has commenced on the Ground Floor.
  • Joinery is in transit and due to arrive in October 2025, with installation to begin from the Ground Floor.

Externally, the team is prioritising façade completion to allow scaffold removal and completion of the external landscaping.

We’re excited by the progress made so far and look forward to sharing the next stages with you as construction continues to move ahead.

Kind regards,
The Society Design Team