January 2026
Dear Parlington Community,
We are delighted to bring you the construction update for the Parlington development, detailing the progress on-site.
Works onsite are as follows:
- The structural frame has been completed and the roof installed, with approximately 95% of capping’s finished.
- The building has been fully wrapped, with first-floor cladding nearing completion. Ground-floor brickwork will commence once scaffolding is removed within the upcoming month.
- External windows and doors have been installed, securing the building envelope.
- All internal rough-in services have been completed to the ground and first floors, with basement services approximately 80% complete.
- Wall and ceiling insulation has been installed throughout.
- Fire-rated plasterboard has been installed to required high-level areas and along adjoining townhouse walls.
- Internal framing and ceiling battens have been installed across all floors, with plaster installation scheduled as the next stage.
- Lift installation is progressing, with approximately 50% now complete.
We're happy to report that construction is still moving along nicely.
We are excited about the progress made and look forward to sharing more updates as construction continues to progress.
Kind regards,
The Parlington Design Team







