July 2026
Dear Parlington Community,
We are delighted to bring you the construction update for the Parlington development, detailing the progress on-site.
Works onsite are as follows:
- External cladding is nearing completion, with the tiles being laid and grouted throughout the rainy weather.
- Landscaping has begun with the waterproofing inside the planter boxes and soil infill following.
- Internally, all joinery carcasses have been installed except the Build in Robes in Townhouse 1-4 bedrooms.
- Tiling and stone have been installed in all powder rooms, with 80% of bathrooms also having the stone and tiles installed (fit-off of the taps/shower roses beginning in unit 5 & 6).
- Stone plinths have been installed under the fireplaces as well as the stone shrouds.
- Lifts have been installed to 50% of the units.
We’re excited by the progress to date and look forward to sharing further updates as works continue. In the meantime, please see the latest imagery from site below.
Kind regards,
The Parlington Design Team