Montview

city

Montview

92 Peel Street, Kew, 3101

Anticipated Completion October 2026

Information

Project Progress

100%

Demolition

100%

Structure

100%

Basement

60%

Fitout

July 2026

Dear Montview Community,

The project is progressing well and remains on track for practical completion in October 2026.

Internal Works

  • The stone benchtops on the Ground Floor have now been fully installed.
  • Timber flooring is currently being installed throughout the Ground Floor apartments.
  • Stone installation for the Level 1 apartments is scheduled to commence in early August.
  • Joinery installation has been completed on both the Ground Floor and Level 1.
  • Joinery installation for Level 2 is expected to commence in early August.
  • Tiling has now been completed across all levels of the building.

External Works & Services

  • The external scaffolding is scheduled to be removed next week, which will significantly improve the building’s appearance.
  • External infrastructure works are progressing well, with electrical works currently underway.
  • The sewer connection has been completed.
  • The water supply is expected to be connected by mid-August.
  • The gas connection is expected to be completed in early August.

We look forward to sharing further updates as construction continues to progress over the coming months. 