May 2026
Dear Montview Community,
Construction at Montview continues to progress steadily, with significant milestones now achieved across both the internal and external works.
Recent Milestones:
- Internally, plaster installation throughout the residences has now been completed.
- Waterproofing works are progressing well , now approximately 80% complete across the project.
- Tiling works have now commenced, with finishes beginning to take shape within the residences and common areas.
- Externally, the façade installation is advancing well , currently at 60% complete.
Subject to ongoing construction progress and authority approvals, the project remains on track for anticipated completion in Q3 2026.
We look forward to sharing further updates as construction continues to progress over the coming months.
Kind regards,
The Montview Design Team





