Authenticated is false

Mercer

plant

Mercer

30 Mercer Road, Armadale, 3143

Information

June 2025

Dear Mercer Purchasers,

Last week , we were pleased to bring you the construction update for the Mercer development, showcasing the progress made on-site.

Works included.

  • Floor structure in first structure complete
  • First floor wall framing in progress
  • Windows ordered, preparing for installation

Following consultation last week with the design team , we now advise the following.

Recently during construction, a number of issues arose which have caused delays to the construction process, including the following:

  • Inclement weather days.
  • Flooding from prolonged periods of rainfall.
  • Delay in procurement of steel and framing materials.
  • Difficulty with site access due to space constraints.
  • Time constraints for logistics due to school zone within vicinity limiting vehicle access.

However , in response to the above, discussions have taken place with D5 (builder) to implement the following actions to address the delayed progress:

  • Appointment of a construction director to provide oversight and drive project delivery
  • Expedite all contracts with subcontractors to be executed within next two months to prevent further delays and maintain construction momentum.
  • Conducting more frequent site inspections to ensure incremental milestones are met and progress remains aligned with target completion date
  • Enhance site logistics and delivery planning to minimise downtime caused by space constraints and restricted transport access
  • Deploying additional labour on-site for carpentry to accelerate framing construction

It is still very much everyone’s desire to complete construction by late 2025 , however given the challenges detailed above, the completion date for construction may be after late 2025 and before the contracted builders period of March 2026.

Going forward , we understand many will need greater clarity to coordinate a move or the sale of another property , and we intend to advise on this with each monthly update to follow . Every party wants to see these terrific town homes completed in alignment with the original completion target of late 2025.

 

Thank you for your patience and anticipated understanding.

Kind regards,

The Mercer Design Team & Marshall White Projects

basement