Dear Laurel Community,

We’re pleased to provide the latest update on the progress at Laurel, where construction is progressing well.

Recently Completed Milestones:

  • The frames to the homes are 100% complete, with the rear garages being finished off by the end of this month.
  • The Huntley Rd homes have achieved lockup, with plaster being hung. The Yawla St homes are due to follow shortly.
  • The cabinetry is now on the way, with quality assurance inspections taking place at the factory this month, with installation to commence before Easter.
  • Park landscaping being tendered, with work due to commence end of April to allow completion to align with the houses in Q3 2026.

Please find the below link to watch the latest update:

https://vimeo.com/1166584929?share=copy&fl=sv&fe=ci

We look forward to keeping you informed as Laurel continues to evolve. In the meantime, we invite you to view the latest site imagery below, offering a glimpse of what’s taking shape behind the scenes.

Kind regards,
The Laurel Design Team