Authenticated is false

First Light

city

First Light

28 Albert Road, South Melbourne, 3205

Anticipated Completion Q2 2027

Information

Project Progress

100%

Demolition

70%

Structure

100%

Basement

20%

Fitout

55%

Total Progress

July 2026

Dear First Light Community,

We’re pleased to share the latest progress on-site, with construction continuing to advance steadily under the management of Ironside and DCF Property.

Works completed throughout June 2026:

  • Jumpform Jump 21 - Complete, now working to Level 22
  • Level 16 slab pour 1 - Complete
  • Level 15 slab pour 1 and 2 - Complete
  • High level services up to Level 10 - Now underway 
  • Window installation preparation works up to Level 15 - Now underway
  • Window installation up to Level 11 - Now underway
  • Precast walls underway to Level 14
  • Plasterboard installation has commenced from Level 9
  • Internal fit-out works underway
    • Level 2 painting complete, tiling complete, joinery, stone and timber floor installation.
    • Level 3 painting complete, tiling complete and joinery installation.
    • Level 4 painting and tiling complete.
    • Level 5 & 6 painting and ceiling works complete.
    • Level 7 sheeting complete and painting has commenced.
    • Level 8-10 shellworks are underway.
  • Passenger lift installation is underway.
  • Laneway reinstatement is complete.

The build is progressing well, with completion and settlement anticipated for Q2 2027.

The below photos provide a glimpse into the activity on site, showcasing the structure now standing high above ground as key service and infrastructure works advance below.

Kind regards,

The First Light Design Team

city