July 2026
Dear First Light Community,
We’re pleased to share the latest progress on-site, with construction continuing to advance steadily under the management of Ironside and DCF Property.
Works completed throughout June 2026:
- Jumpform Jump 21 - Complete, now working to Level 22
- Level 16 slab pour 1 - Complete
- Level 15 slab pour 1 and 2 - Complete
- High level services up to Level 10 - Now underway
- Window installation preparation works up to Level 15 - Now underway
- Window installation up to Level 11 - Now underway
- Precast walls underway to Level 14
- Plasterboard installation has commenced from Level 9
- Internal fit-out works underway
- Level 2 painting complete, tiling complete, joinery, stone and timber floor installation.
- Level 3 painting complete, tiling complete and joinery installation.
- Level 4 painting and tiling complete.
- Level 5 & 6 painting and ceiling works complete.
- Level 7 sheeting complete and painting has commenced.
- Level 8-10 shellworks are underway.
- Passenger lift installation is underway.
- Laneway reinstatement is complete.
The build is progressing well, with completion and settlement anticipated for Q2 2027.
The below photos provide a glimpse into the activity on site, showcasing the structure now standing high above ground as key service and infrastructure works advance below.
Kind regards,
The First Light Design Team