Authenticated is false

First Light

city

First Light

28 Albert Road, South Melbourne, 3205

Anticipated Completion Q2 2027

Information

Project Progress

100%

Demolition

34%

Structure

70%

Basement

5%

Fitout

40%

Total Progress

May 2026

Dear First Light Community,

We’re pleased to share the latest progress on-site, with construction continuing to advance steadily under the management of Ironside and DCF Property.

Works completed throughout April 2026:

  • Jumpform Jump 13 - Complete, Now Working to Level 14
  • Level 10 Slab Pour 1 - Complete
  • Level 9 Slab Pour 1 and 2 - Complete
  • High Level Services up to Level 7 - Now Underway 
  • Window Installation Preparation Works up to Level 10 - Now Underway
  • Window Installation up to Level 6 - Now Underway
  • Internal Walls and Ceiling Works - Now Underway
    • Level 2 and 3 Sheeting, Stopping and Sanding Completed.
    • Level 4 Wall Sheeting and Ceiling Frame Completed.
    • Level 5 Shellworks Completed.
    • Level 6 Shellworks Completed.
  • Car Lift Installation - Complete

The build is progressing well, with completion and settlement anticipated for Q2 2027.

The below photos provide a glimpse into the activity on site, showcasing the structure now emerging above ground as key service and infrastructure works advance below.

Kind regards,

The First Light Design Team

architecture