May 2026
Dear First Light Community,
We’re pleased to share the latest progress on-site, with construction continuing to advance steadily under the management of Ironside and DCF Property.
Works completed throughout April 2026:
- Jumpform Jump 13 - Complete, Now Working to Level 14
- Level 10 Slab Pour 1 - Complete
- Level 9 Slab Pour 1 and 2 - Complete
- High Level Services up to Level 7 - Now Underway
- Window Installation Preparation Works up to Level 10 - Now Underway
- Window Installation up to Level 6 - Now Underway
- Internal Walls and Ceiling Works - Now Underway
- Level 2 and 3 Sheeting, Stopping and Sanding Completed.
- Level 4 Wall Sheeting and Ceiling Frame Completed.
- Level 5 Shellworks Completed.
- Level 6 Shellworks Completed.
- Car Lift Installation - Complete
The build is progressing well, with completion and settlement anticipated for Q2 2027.
The below photos provide a glimpse into the activity on site, showcasing the structure now emerging above ground as key service and infrastructure works advance below.
Kind regards,
The First Light Design Team





