Dear Candela Purchaser,
It’s our pleasure to share the latest quarterly update from the Candela construction site as we continue to make solid progress.
At the end of June 2025, approximately 22.79% of construction works were completed.
Key achievements to date include:
- Retention system and foundation works are now complete
- Civil works have been finalised
- Basement Level 3 slab is complete
- Basement Level 3 Pour 2 and Basement Level 2 Pour 1 have been successfully completed
- Precast panel installation at Basement Level 3 is finished
- Formwork is currently being erected for Basement Level 2 Pour 2
Looking Ahead – Q3 2025 Construction Milestones
In the upcoming quarter, the following milestones are scheduled:
- Completion of the Level 2 suspended concrete slab
- Removal of formwork and back-propping from Basement Levels 1, 2, and 3
- Completion of blockwork walls across Basement Levels 1, 2, and 3
- Services rough-in works completed for Basement Levels 2 and 3, with works underway for Basement Level 1
Milestones for Q3 2025
- Concrete structure Level 2 suspended slab complete
- Formwork and back propping stripped to basement levels 1, 2 & 3
- Blockworks walls complete to basement levels 1, 2 & 3
- Services Rough-In to Basement Levels 2 & 3 complete and services rough-in to basement level 1 underway
With construction in full swing and great progress being made, we’re thrilled to keep the momentum going and look forward to sharing future updates with you.
Take a look at our most recent site photos for a look at the progress firsthand.