Boston

Image of interior design

Boston

16 Boston Road, Balwyn, VIC

Anticipated Completion August 2024
Anticipated Settlement August 2024

Project Progress

100%

Demolition

100%

Structure

100%

Basement

45%

Fitout

May 2024

Dear Boston Purchaser,

We are pleased to again provide an update in relation to your Boston townhome.

- The roof plumbing completed with all defects rectified.
- All plumbing works in the basement including gas and water connections are completed.
- Water tap-in for the water meters is completed.
- Façade cladding completed with minor areas and defects to be rectified.
- Internal plumbing and pipe lagging completed.
- Carpentry & plastering works have started the fixings including skirting and door jambs.
- Main plaster works have been completed and tiling has started.

Please see the latest photos from the construction site. We look forward to providing further updates shortly.

Kind regards,
The Boston Project Team

Image of city