Dear Bakehouse Terraces Community,
We are pleased to share that construction activity is progressing well on site at Bakehouse Terraces.
Key Milestones
- Ground floor services and structure is complete.
- Level 1 structure will be complete next week.
- Level 2 structure is to be completed by the end of July.
- Level 3 structure is to be completed by the end of August.
Long Leadtime Materials now Ordered:
- Passenger lifts
- Timber flooring.
- Tiles.
- Joinery.
- Plumbing fixtures.
- Light fittings.
At this stage, construction completion at Bakehouse Terraces is forecast for April 2027.
We will continue to keep you updated as works progress, in the meantime, please view the latest images from site.