Dear Baie Brighton Community,

We are delighted to bring you the latest construction update for the Baie development, showcasing the progress made on site.

Current Site Progress and Key Milestones

  • The tiling of wet areas is in progress.
  • Internal fences are being installed.
  • Plastering and rendering is near completion.
  • The tiling on the roof terraces and balconies has been completed.
  • The lifts are now installed.
  • Joinery is being installed on site.
  • External works are in progress.
  • Sewer works on street have been completed.

The estimated construction completion is Q2 2026. We look forward to keeping you updated as the project advances.