January 2026
Dear Baie Brighton Community,
We are delighted to bring you the latest construction update for the Baie development, showcasing the progress made on site.
Current Site Progress and Key Milestones
- The tiling of wet areas is in progress.
- Internal fences are being installed.
- Plastering and rendering is near completion.
- The tiling on the roof terraces and balconies has been completed.
- The lifts are now installed.
- Joinery is being installed on site.
- External works are in progress.
- Sewer works on street have been completed.
The estimated construction completion is Q2 2026. We look forward to keeping you updated as the project advances.
In the meantime, we invite you to view the latest site imagery below, offering a glimpse into the evolution of Baie Brighton.
Kind regards,
The Baie Brighton Design Team