Authenticated is false

Baie Brighton

building

Baie Brighton

49 South Road, Brighton, 3186

Anticipated Completion Early 2026

Information

January 2026

Dear Baie Brighton Community,

We are delighted to bring you the latest construction update for the Baie development, showcasing the progress made on site.

Key Milestones

  • Tiling of wet areas underway
  • Internal fences are being installed
  • Plastering and rendering near completion
  • Tiling on roof terraces and balconies in progress
  • Lifts are being installed
  • Joinery in production. Delivery schedule for early to mid-January
  • Hoarding removed, external works in progress
  • Sewer works on street completed

The estimated construction completion is early 2026. We look forward to keeping you updated as the project advances.

In the meantime, we invite you to view the latest site imagery below, offering a glimpse into the evolution of Baie Brighton.

Kind regards,
The Baie Brighton Design Team

person