Anticipated Completion Early 2026

Information

Project Progress

100%

Demolition

70%

Structure

25%

Fit Out

September 2025

Dear Audrey Auburn Community,

We’re pleased to share the latest construction progress at Audrey.

  • Plastering and cladding have been finalised on the rear half of the development, with works on the front half now in motion.
  • Tiling in wet areas has commenced across the rear units, giving interiors a first glimpse of their finished look.
  • Roof installation is complete, ensuring all areas are now fully weather-tight.
  • Joinery shop drawings for the rear units are approved, with production scheduled to begin shortly.

The estimated construction completion is Early 2026.
We will continue to provide updates as construction advances. In the meantime, please see the recent site photos below.

Kind regards,

The Audrey Auburn Design Team