Ascend

building

Ascend

35-37 Whitehorse Road, Blackburn, VIC

Anticipated Completion September 2026

Information

Project Progress

100%

Demolition

70%

Structure

0%

Fitout

November 2025

Dear Ascend Community,

We’re pleased to share the latest construction progress at the Ascend Blackburn, with works continuing steadily on site:

  • All structural steel works have been completed.
  • Ground and first-floor timber framing are complete.
  • Second-floor timber framing is in progress for townhouses TH8–TH14.
  • Roof trusses have been delivered to site.


The estimated construction completion is about late 2026 We’ll continue to keep you updated as key milestones are reached.

In the meantime, please find the latest site photos below.

Kind regards,
The Ascend Design Team