88 Leveson

Image of building

88 Leveson

88 Leveson Street, North Melbourne 3051

Anticipated Completion 1st Quarter 2025
Anticipated Settlement 1st Quarter 2025

August 2024

Dear 88 Leveson Purchaser,

We are thrilled to provide you with an exciting update on the progress of the 88 Leveson townhomes. Construction is moving forward smoothly, and we are on track for completion in the first quarter of 2025. Here are the latest highlights:

Timber Framing: The timber framing for townhomes 2 to 15 is now fully complete. This significant milestone lays the foundation for the next stages of construction.

Windows and Sliding Doors: The installation of windows and sliding doors for townhomes 2 to 15 has been successfully completed.

Façade Framing: Work on the façade framing for townhouses 2 to 15 has commenced. This stage will shape the external look of the townhomes, bringing us closer to the final architectural vision.

Fit-Out: We have started the internal fit-out process for townhomes 2 to 15. This includes the installation of internal walls, electrical, plumbing, and other essential services.

We are excited about the progress made and look forward to sharing more updates as construction continues.

Kind regards,

The 88 Leveson Design Team