Chevron One

Image of city

Chevron One

38 Stanhill Drive, Surfers Paradise, QLD

Anticipated Completion Early 2025
Anticipated Settlement Mid 2025

Information

  • Developed ByBensons Property Group
  • Designed ByMarchese Partners
  • Built ByHutchinson Builders

Project Progress

100%

Demolition

22%

Structure

100%

Basement

0%

Fitout

January 2024

Bensons Property Group is pleased to provide an update on the progress of our upcoming Gold Coast project, Chevron One.

Ground floor profiled precast panels have been installed, with level 1 precast scheduled 01/02/24

Exciting times for Chevron One as we see the superstructure start to cycle upwards and the form presented visually of this Iconic Building.

Decommissioning and removal of the Heavy Metal Treatment system and storage tanks has now been completed
Overheard protection & scaffold support gantry to Basement entry ramp has been installed
Perimeter scaffold has been erected to Level 1
Transfer slab stripping has now been 100% completed
Formwork to Level 1 Pour 1 is currently 90% complete
Formwork to Level 1 Pour 2 is currently 75% complete
Reinforcement & Post Tension install to Level 1 Pour 1 is currently 30% complete
Level 1 Pool Base has been poured with reinforcement to walls & formwork installed
The core from Level 2 to Level 3 has been poured
Fire Stair 03/04 Core has been poured Ground Floor to Level 1
Targeting Level 1 Pour 1 to be completed on 22/01/24 and Pour 2 to be completed on 24/01/24
Targeting Level 1 Precast install 01/02/24