April 2024

Dear Keys Estate Homeowners,

We are delighted to bring you the construction update for the Keys Estate development, detailing the progress made on-site;

  • The civil contractors are about 2 weeks from finishing on site
  • All storm water, sewerage, gas, electrical and NBN services to the lots have been laid and backfilled
  • The civil contractor will run the fire service and complete the main connections to the various authorities
  • The Stage 1 building permit will be issued by the Building Surveyor later this week
  • The builder has organised the concreter to start on site as soon as civil works are completed